This is a short video with Melinda Vaughn, Stan Schultz, Charlie Bass ,Shawn Bass and Heather Morgan.  They do a great job of explaining how FEMA and the USACE worked together to rebuild Joplin's ball fields.  C&M Contractors was the project manager and they had Schultz and Summers Engineering do the design work while Ridge Hill Contractors helped with the construction.

This $1 million project was designed by SSE in just 9 days and C&M completed work and had the fields ready for use 45 days ahead of schedule.      

 